Position 59° 17,6'N 017° 48,6'E; Chart 111

Nautical information

2024-08-19

Time: 2024-08-19 - 2024-08-25.

Swedish Transport Administration communicates that the bridge is closed for all maritime traffic, during the dates stated above.

Time: 4 - 6 Weeks, starting 2024-08-26.

During the times stated above, operational tests will be carried out continuously. The tests include bridge opening, which enables maritime traffic to pass, during the following times:

Monday-Friday at 0930 LT , at 1030 LT , at 1130 LT , at 1230 LT , at 1330 LT.

Weekends and other times: The bridge is closed for all maritime traffic.

 
   

Swing bridge

Vertical clearance: 6 m

Opening hours

May 1 - October 15 

Opening of the bridge is available after request during 10 minutes every half hour between 0630 and 2130. See below for non-opening hours.

16 October - 30 April

Opening of the bridge is available after request during 10 minutes every half hour between 0900 and 1600.

Non-opening hours

The bridge does not open during normal working days Mon-Fri 0540-0930 and 1340-1930.

Contact information

Bridge master: phone +46 (0)70-622 49 68 or +46 (0)73 523 47 75.
Request for bridge opening: Normal working days 0700-2200. Sat-Sun: 0900-1600. Bridge opening shall be made within an hour after request for bridge opening has been received.

Merchant vessels

Merchant vessels may after request receive opening at other times. 

Pleasure craft

The bridge swings out when opening. Please respect the stop signs. 